Higher education and K-12 projects incorporate new educational facility construction, remodels, building renovations or modifications, additions and site infrastructure improvements. Educational project challenges can include special design aspects, tight construction schedules and operational requirements. STRATA personnel work, live and invest in local communities by providing services to assist school district representatives, architects and construction managers with successful educational planning from conceptual stages through post-construction.

Washington State University Martin Stadium
  • Project Name: Washington State University Martin Stadium
  • Location: Pullman, Washington
  • Client: Mrs. Louise Sweeney & Mr. Larry Harris (WSU Capital Planning & Development)
  • Project Cost: $22.5 Million
  • Duration: 2006
  • Value Added: STRATA worked with the design team, and specifically KPFF, on foundation design and construction. Responsive construction testing and inspection enabled WSU and Graham Construction to complete the project between stadium use seasons.

Related Servies

Washington State University Compton Union Building
  • Project Name: Washington State University Compton Union Building
  • Location: Pullman, Washington
  • Client: Mr. Jeff Lannigan (WSU Capital Planning & Development)
  • Project Cost: $80 Million
  • Duration: 2007/2008
  • Value Added: STRATA assisted the structural engineer and Hoffman Construction in evaluating shoring to undermine 2 stories of the structure. Testing and inspection performed on a near continuous basis helped facilitate WSU's interest in quality construction and responsively addressed Hoffman's inspection needs.

Related Servies

Washington State University Academic Center
  • Project Name: Washington State University Academic Center
  • Location: Spokane, WA
  • Client: Mr. Keith Bloom (WSU Riverpoint Campus)
  • Project Cost: 33.8 million
  • Duration: 2004
  • Value Added: Our invaluable relationship with WSU in Pullman, Washington, cultivated in additional project opportunities on the Riverpoint Campus in Spokane, Washington. STRATA personnel provided special inspection and material testing oversight and quality control for the Academic Center and Intercollegiate College of Nursing Buildings.

Related Servies

Valley School District
  • Project Name: Valley School District
  • Location: Valley, Washington
  • Client: Mr. Dax Logsdon (ESD 112)
  • Duration: 2008-2010
  • Value Added: In providing geotechnical continuity from design through construction of several additions and new structures for the Valley School District, STRATA helped to resolve discrepancies associated with anticipated earthwork volumes and consult with the District regarding undocumented fill challenges.

Related Servies

Madison High School
  • Project Name: Madison High School
  • Location: Rexburg, Idaho
  • Client: Mr. Russ Williams (Madison School District #321)
  • Project Cost: $40 Million
  • Duration: 2008 - 2010

Related Servies

Freeman School District
  • Project Name: Freeman School District
  • Location: Freeman, Washington
  • Client: Mr. Sergio Hernandez (Freeman School District)
  • Duration: 2008 - Present
  • Value Added: When unanticipated conditions were encountered during construction, STRATA worked closely with the design, ownership and construction team to develop an aggressive remediation schedule to keep the project milestones intact.

Related Servies

Prairie Wind Elementary School
  • Project Name: Prairie Wind Elementary School
  • Location: Gillette, WY
  • Client: Campbell County School District #1
  • Project Cost: $19 Million
  • Duration: 2009 - 2010
  • Value Added: Through long-standing relationships with Campbell County School District, STRATA local personnel, invested in the community, have served the education sector for nearly 20 years.

Related Servies

Othello School District
  • Project Name: Othello School District
  • Location: Othello, Washington
  • Client: Mr. George Juarez (Othello School District)
  • Duration: 2007-Present
  • Value Added: STRATA provided geotechnical engineering, construction material testing and special inspection services through 6 multi-million dollar school renovations for the same client.

Related Servies

Campbell County High School (South Campus)
  • Project Name: Campbell County High School (South Campus)
  • Location: Gillette, WY
  • Client: Campbell County School District
  • Project Cost: $18 Million
  • Duration: 1996 - 1997
  • Value Added: Through long-standing relationships with Campbell County School District, STRATA local personnel, invested in the community, have served the education sector for nearly 20 years.